University Data Center 5th Anniversary

Posted on: October 14, 2015

 

Last week, we reached a tremendous milestone. The University Data Center (UDC) celebrated five years of operation. The history and timeline is familiar to many of us, and worth repeating:

  • October 5, 2010 – The first test server was installed to verify operations and network connectivity
  • November 2010 through most of 2011 – Significant system migration efforts began, and continued with moving all ITS production services to the UDC
  • October 2015 – The UDC team now supports ITS and more than 50 campus academic and business units and has installed more than 1,000 systems and monitors 1,500 virtual machines.

Congratulations and Happy Anniversary UDC! Learn more on the UDC website.