Group Email Emma Implementation - Update May 2019

Posted on: May 14, 2019

5/14/2019

Contractual negotiations related to the Group Email Emma Implementation project have concluded, and work has resumed.  The project team has revised the schedule for delivery of the new Group Email service, as follows:

  • 6/28:  Completion of build and testing work
  • 7/8 - 7/25:  Emma live training sessions + availability of materials online
  • 7/23:  Emma-based Group Email release for Production use
  • 8/21:  Regroup-based Group Email system retirement

The sub-account structure has been finalized, and build work for the new system is well underway.  Training dates will be announced in early June.

For more information about the Group Email Emma Implementation, please visit https://it.utexas.edu/projects/group_email_emma/overview.